Façade & balcony remediation · 24 apartments · Sample project
● On programme Updated today, 8:14 am
Overview Works register Programme Calendar Documents Team
Progress
62%
31 complete
6 in progress
13 to start
Practical completion forecast 20 Feb
Where works are now
Level 4 balconies Membrane being laid, units 401–406 In progress
East elevation Concrete repairs to slab edges In progress
Level 3 balconies Screed and tiling Complete
Coming up
16 Oct Owner access notice Units 401–406 · emailed to owners Notice
22 Oct Membrane flood test Level 4 · engineer witness Inspection
27 Oct Committee progress meeting Online · 6:00 pm Meeting
Programme
SEP OCT NOV DEC JAN FEB
Investigation Scaffold & access Balcony membranes Façade repairs Close-out
PC
TODAY
Drawing & document register
RW-101 Balcony details Issued 9 Oct · current Rev C
RW-101 Balcony details Superseded 9 Oct Rev B
RW-200 Façade elevations Issued 2 Oct · current Rev A
ENG-04 Engineer's inspection report Uploaded 7 Oct v2
Project team
SM Strata manager Your agency
OC Owners committee Chair & members
PC Pelcon Project manager
EN Engineer Remedial design
BL Builder Remedial contractor